Achievements 2025

Long-Term Excellence in Operation & Maintenance at PLTU Cilacap Unit 1 & 2 (2x300 MW)

05 / 06 / 2025 - Project Date

Since 2008, D&C has proudly served as the Operation & Maintenance (O&M) contractor for PLTU Cilacap Unit 1 and 2, each with a capacity of 300 MW. Over more than 15 years of continuous operation, D&C has consistently demonstrated high-performance standards, maintaining an Availability Factor of over 80%, contributing significantly to reliable electricity supply in Central Java.

This long-term partnership with PT Sumber Segara Primadaya (S2P) reflects D&C’s commitment to operational excellence, safety, and efficiency in managing large-scale coal-fired power plants. Our team’s technical expertise, proactive maintenance strategies, and dedication to service quality have made PLTU Cilacap one of the key contributors to the region’s energy stability.

The excellent work of D&C has propelled PLTU Cilacap to be nationally recognized as the Best IPP in Indonesia in 2015 and 2023.